Terminal 2 Out of Gauge Std. 3 HBS Upgrade


ree

Client: Beumer (UK) Ltd 

Project Duration: 8 weeks 

Project Value: £200k 

Project Description: Upgrade of the Out of Gauge Baggage conveyor system. 

 

Upgrade of the Out of Gauge Baggage conveyor system and integration of 2 no. new Std.3 EDS machines, including development and implementation of temporary operational mitigations to ensure no operational impact. Completion of this project on time ensured that the airport achieved DfT compliance. 




 
 