Temporary Outbound Baggage System – Complete Electrical Installation

Client: ACS Ltd / London City Airport
Project Duration: 10 Months
Project Value: £1.1m
MEP Project Description:
Greenfield site installation, testing and commissioning of all Power, Lighting, Fibre, Structured Cabling, CCTV and Access Control systems within a purpose built structure to house a new Std. 3 Baggage Handling System for the airport.
Baggage System Project Description:
Installation & Testing of a new combined In Gauge and Out of Gauge Baggage Handling System at LCY that will enable the airport to be Std. 3 compliant. The ‘TOBB’ building adjacent to the LCY runway will transport outbound baggage product from check-in to make-up and includes integration of Automatic Tag Reading Equipment, Hold Baggage Screening Machines, Vertical Sortation Units, Vertical Transportation Units and a make-up carousel.