Temporary Outbound Baggage System – Complete Electrical Installation



Project Duration: 10 Months 

Project Value: £1.1m 

 

MEP Project Description: 

Greenfield site installation, testing and commissioning of all Power, Lighting, Fibre, Structured Cabling, CCTV and Access Control systems within a purpose built structure to house a new Std. 3 Baggage Handling System for the airport. 

 

Baggage System Project Description: 

Installation & Testing of a new combined In Gauge and Out of Gauge Baggage Handling System at LCY that will enable the airport to be Std. 3 compliant. The ‘TOBB’ building adjacent to the LCY runway will transport outbound baggage product from check-in to make-up and includes integration of Automatic Tag Reading Equipment, Hold Baggage Screening Machines, Vertical Sortation Units, Vertical Transportation Units and a make-up carousel. 




 
 