PROJECT: LONDON HEATHROW AIRPORT TERMINAL 2 Direct System Standard 3 Compliance HBS Upgrade
Project Duration: 4yr
Project Value: £7m
Project Description: Installation of a new baggage system within Terminal 2.
Installation was completed in a phased approach to ensure there was no impact to live operation. The existing system (approx. 1.2km of conveyor) was decommissioned and removed before being replaced with a new system including the integration of 7 no. Std. 3 HBS machines to ensure the airport achieved Std.3 Department for Transport compliance.